due date # Jinlong (Trajectories) Khalid (WPS Admin) Mohammad (Open Sensor Search) Patrick (Seismic SOS)
  org admin mentor org admin mentor org admin mentor org admin mentor
June 24 1 DONE - DONE DONE DONE DONE DONE DONE AK, good
July 1 2 DONE - DONE DONE DONE DONE DONE DONE
July 8 3 DONE - DONE DONE late, but DONE DONE DONE DONE
July 15 4 DONE - DONE DONE DONE DONE DONE DONE
July 22 5 DONE - DONE DONE DONE DONE DONE DONE
July 29 6 DONE - DONE DONE DONE DONE DONE DONE
August 5 7 DONE - DONE DONE DONE DONE DONE DONE
August 12 8 DONE - DONE DONE DONE DONE DONE DONE
August 19 9 DONE - DONE DONE DONE DONE DONE DONE
August 26 10 DONE - DONE DONE DONE DONE DONE DONE
September 2 11 DONE - DONE DONE DONE DONE DONE DONE
September 9 12 DONE - DONE DONE DONE DONE DONE DONE
September 16 13 DONE - DONE DONE - - DONE DONE
September 23 14 DONE - DONE DONE - - - -

Blog Articles

How to write a blog article: GSoCGuidelines

Article due days: The day the article is published on the blog. Plan ahead to deliver a draft version at least two working days before that day!

  Jinlong (Trajectories) Khalid (WPS Admin) Mohammad (Open Sensor Search) Patrick (Seismic SOS)
First Blog Entry DONE http://blog.52north.org/2013/06/20/trajectory-analysis-in-r/ DONE http://blog.52north.org/2013/06/18/new-52-north-wps-admin-web-application/ DONE http://blog.52north.org/2013/06/21/open-sensor-search/ DONE http://blog.52north.org/2013/06/19/seismic-modeling-using-sos-and-swe/
Second Blog Entry DONE http://blog.52north.org/2013/08/01/trajectory-analysis-in-r-midterm-post/ DONE http://blog.52north.org/2013/07/30/52-north-wps-configuration-management-reloaded/ DONE http://blog.52north.org/2013/08/02/opensensorsearch-midterm-blog/ DONE http://blog.52north.org/2013/07/31/seismic-observations-in-sos-midterm-report/
Third Blog Entry DONE http://blog.52north.org/2013/09/24/trajectory-analysis-in-r-final-post/ DONE http://blog.52north.org/2013/09/17/meet-the-new-52-north-wps-admin-web-application/ DONE http://blog.52north.org/2013/09/19/opensensorsearch-final-blog-post/ DONE http://blog.52north.org/2013/09/20/seismic-observations-in-sos-final-report/

Status in this table: unchecked = no draft yet, checked = draft available, DONE = published

CLAs

  • checked Jinlong
  • checked Khalid
  • checked Mohammad
  • checked Patrick